| February 28 | Annual generation output published on OASIS |
| April 30 | 18 Month Forecast & Assessment update published on OASIS |
| June 30 | 10 Year System Plan posted on OASIS |
| November 3 | MP-09 Annual Outage Planning: Preliminary transmission system outage plan posted on OASIS |
| November 18 | MP-09 Annual Outage Planning: Generation Market Participants' preferred plans due to NSPSO Customer impact review of transmission outage plan due to NSPSO |
| October 31 | 18 Month Forecast & Assessment update published on OASIS |
| November 30 | MP-09 Annual Outage Planning: NSPSO initial review and feedback due to Transmitter and Generation Market Participants |
| December 17 | MP-09 Annual Outage Planning: Transmitter and Generation Market Participants' revisions to outage plans due to NSPSO |
| December 30 | MP-09 Annual Outage Planning: NSPSO notifications of approval or rejection of annual outage plan due to Transmitter and Generation Market Participants. |