Nova Scotia Power

Transmission Operations

Transmission Planned Outage Schedule

 

Posted: 2015-07-31; 13:47

 

Circuit/

Element

Start Date

Return Date

Notes

Work

Status

NB STOP

15J03

2015-02-27

2015-12-31

NB loads 2300 3100 = Tie 200 to 140 respectively

In Progress

NB STOP 15J17

2015-08-04

2015-08-20

NB to (NS + PEI) total flows to 350 MW.

Pending

NS STOP 15J16

2015-08-04

2015-08-04

NB to NS flows limitied to 100MW. Limit the flows NS to NB to 200MW.

Pending

67N-T82

2015-05-19

2015-08-10

Onslow Import Limit 800 MW. CBX Normal. NB Tie Restrictions Apply based on Generation.

In Progress

67N-T82 + 67N-B9

2015-08-10

2015-08-13

Onslow Import Limit 800 MW. CBX Normal. NB Tie Restrictions Apply based on Generation.

Pending

88S-713

2015-07-16

2015-07-31

Repairs. No Restrictions

In Progress

L-7003

2015-08-04

2015-08-31

CBX limited to 620MW Onslow Import limited to 755 MW. 2 Units available for SPS targeting.

In Progress

L-6539

2015-08-10

2015-08-10

Maintenance. Generation Restrictions Apply

Pending

L-6513

2015-08-24

2015-08-26

Maintenance. No Restrictions

Pending

 

L-7019

2015-09-08

2015-10-01

Upgrades. CBX limited to 620, ONS 755

Pending

(Only transmission lines rated 138kV and higher that limit bulk power transfers are listed)