Posted: 2014-07-23; 13:43

 

Circuit/

Element

Start Date

Return Date

Notes

Work

Status

NB Transmission Restriction- 14J10

2014/03/27

2014/11/30

NB to NS limited 150

PEI + NS limited to 300 MW

In Progress

88S-SPS-RTU

2014-06-02

2014-07-31

No Restrictions

In Progress

88S-T71 / L-6533

2014-07-14

2014-07-31

Generation Restrictions Apply

88S-T72 170MW

In Progress

L-6549

2014-07-13

2014-07-24

Generation Restrictions Apply

In Progress

L-7004

2014-07-2/

2014-08-07

Lower SPS arming Limits ( possible 2units)

CBX 620

Onslow Import 755

In Progress

3C-T71

2014-07-22

2014-07-24

No restrictions

In Progress

120H-T71

2014-07-21

2014-08-13

Flow into Metro 400 to 500MW depending on Temp

Pending

88S-T72

2014-07-29

2014-08-07

Generation Restrictions Apply

East End Export 800 MW

Pending

88S-713 & 720

2014-07-29

2014-08-07

See 88S-T72

Pending