Nova Scotia Power

Transmission Operations

Transmission Planned Outage Schedule

 

Posted: 2014-09-18; 15:49

 

Circuit/

Element

Start Date

Return Date

Notes

Work

Status

NB Transmission Restriction 14J10

2014/03/27

2014/11/30

NB to NS limited 150

PEI + NS limited to 300 MW

In Progress

NB Transmission Restriction

2014/09/13

2014/09/27

NB to NS Limited to 100 MW

In Progress

L-6545

2014-09-15

2014-09-27

Generation Restrictions apply

In Progress

L-7003

2014-09-8

2014-10-2

CBX- 400 - 850

Onslow Import 755 / 795

SPS arming

In Progress

L-6516

2014-09-8

2014-10-2

CBX 400 - 850

Generation Restrictions Apply

SPS targeting

In Progress

L-6515

2014-09-19

2014-09-19

Generation restrictions apply

Lower SPS targeting values

Pending

L-6007

TBD

TBD

Generation restrictions apply

Pending

101S-T81

2014-9-22

2014-10-1

Hastings From 600MW to 625*

L7011+L7012 500 to 600

Mainland at Hastings 590 to 680

*can be 675 if CBX is below 540

Generation Restrictions apply

Lower SPS arming applied

Pending

L-8004

2014-09-22

2014-09-22

Hastings From 600MW to 625*

L7011+L7012 500 to 600

Mainland at Hastings 590 to 680

*can be 675 if CBX is below 540

Generation Restrictions apply

Lower SPS arming applied

Pending

L-7002

201409-23

2014-09-23

Onslow South 670 to 850

Pending

(Only transmission lines rated 138kV and higher that limit bulk power transfers are listed)