Posted: 2010-09-09; 12:26
|
Circuit/ Element |
Start Date |
Return Date |
Notes
|
Work
Status
|
|
L-8002 |
2010/09/07
08:00 |
2010/09/14
17:00 |
Transmission
line upgrading Flow
into Metro limit 500 MW |
In
progress |
|
L-7004 |
2010/09/15
07:00 |
2010/09/21
17:00 |
Transmission
line structure repairs Onslow
Import limit 780 MW |
Pending |
|
L-7019 |
2010/09/22
07:00 |
2010/10/7
17:00 |
Transmission
line structure repairs Onslow
Import limit 755 MW |
Pending |
(Only
transmission lines rated 138kV and higher that limit bulk power transfers are
listed)
For
help, contact: