Posted: 2012-02-01; 12:57
|
Circuit/ Element |
Start Date |
Return Date |
Notes
|
Work
Status
|
|
L-6535/L-1159 |
20/2/2012
07:00 |
2/3/2012
16:00 |
Isolation
required for tap construction and 30N terminal protection changes |
Pending |
(Only transmission lines rated 138kV and
higher that limit bulk power transfers are listed)
For
help, contact: