Nova Scotia Power

Transmission Operations

Transmission Planned Outage Schedule

 

Posted: 2014-07-30; 13:26

 

Circuit/

Element

Start Date

Return Date

Notes

Work

Status

NB Transmission Restriction- 14J10

2014/03/27

2014/11/30

NB to NS limited 150

PEI + NS limited to 300 MW

In Progress

88S-SPS-RTU

2014-06-02

2014-08-01

No Restrictions

In Progress

88S-T71 / L-6533

2014-07-14

2014-08-08

Generation Restrictions Apply

88S-T72 170MW

In Progress

L-7004

2014-07-2/

2014-08-07

Lower SPS arming Limits (2units)

CBX 620

Onslow Import 755

In Progress

120H-T71 / B71

2014-08-05

2014-08-08

Flow into Metro 500MW

Pending

88S-T72

TBD

TBD

Generation Restrictions Apply

East End Export 800 MW

Pending

88S-713 & 720

TBD

TBD

See 88S-T72

Pending

(Only transmission lines rated 138kV and higher that limit bulk power transfers are listed)