Nova Scotia Power

Transmission Operations

Transmission Planned Outage Schedule

 

Posted: 2015-06-30; 14:41

 

Circuit/

Element

Start Date

Return Date

Notes

Work

Status

NB STOP

15J03

2015-02-27

2015-12-31

NB loads 2300 3100 = Tie 200 to 140 respectively

In Progress

67N-T82

2015-05-19

2015-07-10

CBX limited to 500 MW and ONS limited to 600 MW. Generation restrictions are in place.

In Progress

L-6511

2015-06-22

2015-07-31

Onslow Import limited based on Generation. Reduced SPS Arming Limits.Other Generation Restrictions Apply. This line will be switched in end of day Tuesday June 30th, and back out on Monday July 6th.

In Progress

L-7005

2015-06-29

2015-07-16

L7005 is out of service. Cape Breton Export is limited to 620MW and the Onslow Import is limited to 755MW

In Progress

L-6503

2015-07-01

2015-07-01

Maintenance. Onslow Import 760 MW. Generation Restrictions Apply.

Pending

30N-614

2015-07-02

2015-08-14

Capital Replacement. No Restriction.

Pending

1H-T62 & T62G

2015-07-02

2015-07-03

Maintenance. Restrictions TBD

Pending

L-7014

2015-07-02

2015-07-16

Maintenance. Generation Restrictions Apply

Pending

120H-714

2015-07-06

2015-07-13

Maintenance. No Restrictions.

Pending

L-6539

2015-07-08

2015-07-08

Protection upgrades. Generation Restrictions Apply

Pending

120H-720

2015-07-09

2015-07-10

Maintenance. No Restricctions

Pending

(Only transmission lines rated 138kV and higher that limit bulk power transfers are listed)

For help, contact:

oasisadmin@nspower.ca